The first phase of sealing and restriping is complete. Lots 1, 2 and 4 (see picture below) are complete and available for use.
We will start Phase II Tuesday, September 9. All cars need to be relocated from lots 3 and 5 to the street or lots 1, 2, and 4 by 8 am on Tuesday, September 9th through Thursday, September 11th.
The process will go like this for lots 3 & 5:
- first seal coat applied Tuesday, September 9th
- second seal coat applied Tuesday, September 9th
- parking lot will cure Wednesday, September 10th - hopefully we will be able to stripe then, but more than likely...
- stripes will be painted the morning of Thursday September 11th. Parking lot should be available for use the evening of Thursday September 11th.